Denied Interest — False promise in advertisement - Ekta World
Complain ID : JGJN031374 79
- State : Maharashtra
- City : Mumbai
- Address: Room - 659, Chawl No - 33, Valanai Colony, Orlem, Malad - West. Mumbai - 400064
From the date of booking i.e. July 2016, Ekta World kept on sending demand letters every 2 months without any progress in construction. Eventually my bank denied the payment as there was no progress in construction work of my wing. I have already paid 82% of the flat cost.
My wings fit-out date was August 2017. However there was no work done in my wing from July 2016 to August 2017. When I called Ekta World in August 2017 for getting the interest for delay in construction work as promised in their advertisement and initial sales process, I was told that there is a 6 months grace period and they will start construction work of my wing from October 2017 and by February 2018 if the wing is ready upto fit out then I will be eligible to get interest for delay in construction.
However there was no progress in construction work till February 2018. When I called Ekta World again in February 2017 for getting the interest for delay in construction work as promised in their advertisement and initial sales process, I was told that Ekta World has paid the premium but the insurance company which covered this interest for delay is closed. Further I was called to their Bandra office for a discussion with their director on 23 February 2018, who told me Ekta World does not pay any interest. In the end of the discussion they told me to allow them some more time to revert to me on this issue.
I sent them email of this discussion and kept on chasing them via email and phone calls. Eventually after 40 days from my discussion I received an email reply from Ekta World as "We deeply regret for the inconvenience caused to you . This is to inform you that we have already started and completed the brick work up to the 8th Slab for your said wing . We shall endeavour to complete the building construction much before the mentioned date on the RERA website of 31 July 2020 and are working towards it ."
I am asking them to pay the interest for delay in construction work (fit out) as promised by them in the advertisement and sales process and instead of paying me the interest they are saying they will give possession of the flat on time.
Related complaints
-
ENKAY BUILDERS Bought flat at Enkay Garden 3 years back and still waiting for PossessionMadhavan Ramaswamy / Real Estate Complaint / January 1, 2018 / Mumbai / MaharashtraIf I have made any mistake in my life, it would be buying a flat in Enkay Garden. They always give fake promises which will never be implemented at ground level. I bought a Flat on Phase II 2 years back and they promised to give possession in 1 year....
-
Advance Maintainance Transfer issue against COSMOS LIFESTYLEsarang joshi / Real Estate Complaint / December 22, 2017 / Thane / MaharashtraSub: Regarding the Advance Maintenance Amount issue for Cosmos Jewels , Ruby 1 Flat 1A-1B. I am the resident of cosmos Jewels and Purchase the above said property from Cosmos Lifestyle dated 18th feb 2017 as per the registered agreement TNN5-1725-201...
-
Refund of amount paid against flat after cancellation, Lok Nagari Developers, MIDC RoadVivek Kaushal / Real Estate Complaint / October 30, 2017 / Kalyan-Dombivali / MaharashtraThe Sales Manager, Lok Nagari Developers, MIDC Road, Ambernath (East) – 421 506 Sub: Cancellation of Flat no. A9/706 (Refer letter dated 05.07.15, 10.04.16, 28.08.16, 07.11.16 & 28.09.17) This is to inform you that I have booked my flat no. 201 o...
-
Builder not giving possession complaint against Puraniks BuildersAringunram / Real Estate Complaint / October 16, 2017 / Thane / MaharashtraSir, We beg for your help. We had used most of our savings to purchase a flat in a residential complex, called Rumah Bali, developed by Puraniks Builders in Thane. Possession was promised in May 2015. We are yet to get the keys to our flat. We had pa...
-
Complaint non possession of flat booked flat in Nirmal Lifestyle (kalyan)pvt ltd township in 2011sanju arora / Real Estate Complaint / September 28, 2017 / Mumbai / Maharashtrai had booked flat in Nirmal Lifestyle (kalyan)pvt ltd township in 2011 and was promised possession in 3 yrs. the project kept dealing and agreement was done in April 2014with a clause of possession to be given in June 2016 and grace period of 6 month...
-
Society not formed, we are 10members of our Pushp Mandir Society living from last 16yearsNikhil Wader / Real Estate Complaint / July 5, 2017 / Panvel / MaharashtraSir, we are 10members of our Pushp Mandir Society living from last 16years but every year builder f=give excuses and delay the subjected work. Also we submitted all required documents but still not taking any action from him.